Dock Brook Flood Risk Management

Dock Brook Outfall

Dock Brook Outfall

Client: West Lancashire Borough Council

Value: £254,000

Programme: 20 weeks

Completion Date: May 2012

This project for West Lancashire Borough Council was to provide surface water drainage improvements to Dock Brook at Parbold. The working areas are spread across three individual sites and involve regrading, reprofiling and bank reinforcement to 165m of existing channel in Dock Brook, construction of a new 50m long flood bund to the rear of residential properties, relining 37m of existing culvert, clearing out over 100m of existing 825mm pipe, construction of over 100m of new 900mm dia culvert, construction of new inlet and outfall into the River Douglas.