The latest and last update for 2019 from Dogs Trust Cardiff shows the site progressing well despite the poor weather. The first floor slab to the Rehoming building has been cast and roofing work is taking place along with roof light installation. Brickwork to the Stray & Reclaim building has been laid and the Maintenance building floor slab has been cast. The access road has been fully tarmaced to binder and construction of the exterior dog runs continues.
More to follow from South Wales next year!