PROJECT SPOTLIGHT: THE TRANSFORMATION OF TELFORD FIRE STATION

Originally built in the 1970s, Telford Central Fire Station had grown outdated and challenging for modern emergency operations. It served as a vital hub for Shropshire Fire and Rescue Service, but the ageing structure no longer met current fire service needs or regulations.

In 2021, McPhillips were awarded a £9 million contract for redevelopment of the station, and preparations began to deliver a complete transformation. The building had to be reconfigured to face 21st-century challenges, and act as a resilient, state-of-the-art facility for emergency response, training, and community engagement.

A challenging scope from the start

The project demanded more than a cosmetic update; it was a complete reworking of an outdated and restrictive layout. The station’s old plant and services were near the end of their lifecycle, and essential areas like IT systems and decontamination zones were in dire need of updates.

McPhillips aimed to preserve parts of the existing substructure and frame, but as Paul Inions, McPhillips’ Managing Director, explained, that proved to be more complex than initially anticipated.

“The original scope of this scheme involved stripping down the existing building to its structural frame and re-cladding, reorganising the internal spaces to improve functionality and critical operations, plus single and two-storey extensions to create more floorspace.

“However, as work progressed, we discovered that parts of the existing frame, specifically the lattice beams, couldn’t meet current fire regulations. The complexity of retaining structural stability and supporting existing concrete floors during the replacement process required a bespoke temporary works design and the installation of support steelwork used as the lattice beams were removed and replaced sequentially throughout the building.”

Ultimately, replacing these beams was unavoidable, which called for a highly specialised approach to maintain the building’s integrity.

Tackling the build with an innovative, phased approach

Given the challenges these discoveries presented we moved to mitigate the inevitable delays by temporarily wrapping the building to enable internal works to progress where possible.

“Working with our structural steelwork subcontractor and structural engineer, we developed a sequence that allowed construction in areas where beams had been replaced,” Paul recalls. This flexible approach kept the project moving forward despite the hurdles we encountered along the way.

Community and client-centred design

Alongside updating the facility’s operational capacity, the project aimed to make the station a more welcoming place for community use and interagency collaboration. The station was fitted with new spaces for community events and training, and also includes facilities for multi-agency emergency command coordination.

Overcoming unexpected setbacks

The project wasn’t without its challenges. Beyond the structural discoveries, there were on-site environmental constraints, including the need to protect a local newt population. Asbestos removal added further complexity. Even so, our team remained committed to delivering a high-quality outcome.

Despite these obstacles, we delivered a facility that not only met operational needs but also strengthened community ties. Mark Kiddie, McPhillips’ Marketing & Business Development Manager, summed up the local pride felt throughout the project: “As a Telford business, we’re delighted that the client shared our vision for supporting the local economy – locally employed people worked on the delivery of this project throughout.”

Reflecting on the changing scope of works, Paul Inions is proud of the finished build, saying: “Despite the complications, and the contractual challenges that ensued, the final outcome is a first-class facility for Shropshire Fire Authority.”

Key features of the new Telford Fire Station

The redeveloped station now stands as a flagship facility, combining state-of-the-art emergency preparedness with a sustainable, community-focused design — proof of McPhillips’ commitment to overcoming challenges and delivering excellence.

Future proofed infrastructure: Updated mechanical systems, ICT, and electrical services to handle the latest emergency response technology.

Multi-agency command and training facilities: Allows joint training with police, ambulance, and emergency response teams.

Sustainable / green building elements: Photovoltaic panels and other eco-friendly upgrades combine to reduce the building’s carbon footprint.

Enhanced community spaces: Offers a welcoming environment with areas dedicated to community engagement and training events.

Why choose McPhillips for Public Sector construction?

This project continued our track record for delivering complex infrastructure under challenging conditions, underscoring our capabilities in asset optimisation, community engagement, and commitment to green technology.

For stakeholders seeking a partner that prioritises resilience, efficiency, and community value, McPhillips offers the expertise, adaptability, and dedication needed to bring transformative projects to life.

If you’re looking to blaze a trail with your new building project, contact our building department on: 01952 670440 or email: mcphillips@mcphillips.co.uk

Contact Us    More Projects

Project Images

Contact Us